| Introduction.
Fire can break out on most construction
sites. There are around 11 construction fires every day. As you
read this publication there is probably a fire on a construction
site. Not only can people be killed or injured, but fires can also
be financially devastating to those involved.
This page sets out some basic measures
for construction fire safety and is aimed mainly at those managing
and working on smaller sites where risks are relatively low (but
it should not be assumed that risks are low merely because a site
is small). More detailed guidance is also available aimed at higher
risk sites and there is much in it that is relevant for any construction
site. Its reference is given at the end of this information sheet.
Legal requirements
The Construction (Design and Management) Regulations
2007 (CDM 2007) came into force in Great Britain on 6 April 2007,
and is divided into 5 parts:
- Part 1 deals with the application of the Regulations
and definitions.
- Part 2 covers general duties that apply to all
construction projects.
- Part 3 contains additional duties that only apply
to notifiable construction projects, i.e. those lasting more that
30 days or involving more than 500 person days of construction
work.
- Part 4 contains practical requirements that apply
to all construction sites.
- Part 5 contains the transitional arrangements
and revocations.
Background to the new Regulations.
Construction remains a disproportionately dangerous
industry where improvements in health and safety are urgently needed.
The improvements require significant and permanent changes in dutyholder
attitudes and behaviour. Since the original CDM Regulations were
introduced in 1994, concerns were raised that their complexity and
the bureaucratic approach of many duty holders frustrated the Regulations
underlying health and safety objectives. These views were supported
by an industry-wide consultation in 2002 which resulted in the decision
to revise the Regulations.
The new Regulations revise and bring together the
CDM Regulations 1994 and the Construction (Health Safety and Welfare)
Regulations 1996 into a single regulatory package.
The new regulations require measures both to prevent
fires happening and to make sure all people on construction sites
(including visitors) are protected if they do occur. The relevant
fire safety sections are 38 to 41 inclusive which are,
Regulation 46 Enforcement in respect of fire
(1) Subject to paragraphs (2) and (3)
- (a) in England and Wales the enforcing authority
within the meaning of article 25 of the Regulatory Reform (Fire
Safety) Order 2005(a); or
- (b) in Scotland the enforcing authority within
the meaning of section 61 of the Fire (Scotland) Act 2005(b)
shall be the enforcing authority in respect of a
construction site which is contained within, or forms part of, premises
which are occupied by persons other than those carrying out the
construction work or any activity arising from such work as regards
regulations 39 and 40, in so far as those regulations relate to
fire, and regulation 41.
(2) In England and Wales paragraph (1) only applies
in respect of premises to which the Regulatory Reform (Fire Safety)
Order 2005 applies.
(3) In Scotland paragraph (1) only applies in respect
of premises to which Part 3 of the Fire Scotland) Act 2005 applies(c).
Note. In an existing non domestic premises in
which the The Regulatory Reform (Fire Safety) Order 2005 (RR(FS)O)
or Fire (Scotland) Act 2005 applies and is undergoing contruction
work the Order or Act is enforced by the Fire and Rescue Service
(FRS).The Fire and Rescue Service is also the enforcing authority
for sections 38 to 41 of the CDM 2007.
In a new build sections 38 to 41 of the CDM
2007 is enforced by the HSE.
Regulation 38. Prevention of risk from fire
etc.
(1) Suitable and sufficient steps shall be taken
to prevent, so far as is reasonably practicable, the risk of injury
to any person during the carrying out of construction work arising
from
- fire or explosion;
- flooding; or
- any substance liable to cause asphyxiation.
Regulation 39.Emergency procedures
(1) Where necessary in the interests of the health
and safety of any person on a
construction site, there shall be prepared and, where necessary,
implemented suitable and
sufficient arrangements for dealing with any foreseeable emergency,
which arrangements shall
include procedures for any necessary evacuation of the site or any
part thereof.
(2) In making arrangements under paragraph (1),
account shall be taken of,
- the type of work for which the construction site
is being used;
- the characteristics and size of the construction
site and the number and location of places
of work on that site;
- the work equipment being used;
- the number of persons likely to be present on
the site at any one time; and
- the physical and chemical properties of any substances
or materials on or likely to be on the site.
(3) Where arrangements are prepared pursuant to paragraph
(1), suitable and sufficient stepsshall be taken to ensure that,
- every person to whom the arrangements extend is
familiar with those arrangements; and
- the arrangements are tested by being put into
effect at suitable intervals.
Regulation 40. Emergency Routes and Exits
(1) Where necessary in the interests of the health
and safety of any person on a construction site, a sufficient number
of suitable emergency routes and exits shall be provided to enable
any person to reach a place of safety quickly in the event of danger.
(2) An emergency route or exit provided pursuant
to paragraph (1) shall lead as directly as possible to an identified
safe area.
(3) Any emergency route or exit provided in accordance
with paragraph (1), and any traffic route giving access thereto,
shall be kept clear and free from obstruction and, where necessary,
provided with emergency lighting so that such emergency route or
exit may be used at any time.
(4) In making provision under paragraph (1), account
shall be taken of the matters in regulation 39(2).
(5) All emergency routes or exits shall be indicated
by suitable signs.
Regulation 41. Fire detection and fire-fighting
(1) Where necessary in the interests of the health
and safety of any person at work on a construction site there shall
be provided suitable and sufficient,
- fire-fighting equipment; and
- fire detection and alarm systems, which shall be suitably located.
2) In making provision under paragraph (1), account
shall be taken of the matters in regulation 39(2).
(3) Any fire-fighting equipment and any fire detection
and alarm system provided under paragraph (1) shall be examined
and tested at suitable intervals and properly maintained.
(4) Any fire-fighting equipment which is not designed
to come into use automatically shall be easily accessible.
(5) Every person at work on a construction site
shall, so far as is reasonably practicable, beinstructed in the
correct use of any fire-fighting equipment which it may be necessary
for him to use.
(6) Where a work activity may give rise to a particular
risk of fire, a person shall not carry out such work unless he
is suitably instructed.
(7) Fire-fighting equipment shall be indicated
by suitable signs.
Guidance on The Construction (Design and
Management) Regulations 2007
The new regulations are supported
by an Approved Code of Practice (ACoP).
The Approved Code of Practice (ACoP)
has special legal status and gives practical advice for all those
involved in construction work. If you follow the advice in the
ACoP you will be doing enough to comply with the law in respect
of those specific matters on which it gives advice and includes
a copy of the Regulations.
The ACoP explains:
- The legal duties placed on clients, CDM co-ordinators,
designers, principal contractors, contractors, self-employed
and workers.
- The circumstances in which domestic clients
do not have duties under CDM 2007 (but that the regulations
still apply to those doing work for them).
- Gives information on the new role of CDM co-ordinator
– a key project adviser for clients and responsible for
coordinating the arrangements for health and safety during the
planning phase of larger and more complex projects.
- Which construction projects need to be notified
to HSE before work starts and gives information on how this
should be done.
- How to assess the competence of organisations
and individuals involved in construction work.
- How to improve co-operation and co-ordination
between all those involved in the construction project and with
the workforce.
- What essential information needs to be recorded
in construction health and safety plans and files, as well as
what shouldn’t be included.
What the law requires in practice will vary depending
on the risks. Erecting a simple steel framed building in the middle
of a field will only require simple precautions because fire risks
are low. Higher risk work such as refurbishing floors in an occupied
office block, will need many more precautions because the risk
of fire occurring and the difficulties of escaping from it are
much greater.
Prevent fire occurring
Most construction fires have simple causes and
can be dealt with by simple precautions. The following are particularly
important:
-
Make sure that LPG cylinders and other flammable
materials are properly stored. LPG should be stored outside
buildings in well-ventilated and secure areas. Flammable materials
such as solvents and adhesives should be stored in lockable
steel containers;
-
LPG supplies should be turned off at the cylinder
when not in use. This is particularly important out of hours.
Serious explosions have occurred after site huts have gradually
filled with gas because an LPG heater has not been turned
off. Also make sure site huts are adequately ventilated and
do not keep LPG in them if it is not needed;
-
Make sure that LPG equipment and fittings
are properly maintained. Damaged hoses and fittings or makeshift
connections are extremely dangerous because they can easily
lead to leaks in tough construction conditions;
-
If there is any suspicion that LPG is leaking
stop using it and check. Leaks can be identified by hissing,
smell or using soapy water, but never with a naked flame.
Only light up when you are certain that there are no leaks
and that any vapour which has leaked has dispersed;
-
Follow clear rules for hot work such as welding.
Formal permit-to-work systems are often appropriate. In particular,
make sure extinguishers are at hand and that sparks or heat
cannot set fire to surrounding materials. After the work has
finished (usually an hour later) check the worksite to make
sure that there is no smouldering;
-
Do not leave tar boilers unattended;
-
Keep a tidy site and make sure rubbish is
cleared away promptly and regularly;
-
Avoid unnecessary stockpiling of combustible
materials, e.g. polystyrene, and store what is necessary away
from ignition sources. Limit what is taken onto site from
the store to what is needed for a day's work;
-
Consider the need for special precautions
in areas where flammable atmospheres may develop, such as
the use of volatile solvents or adhesives in enclosed areas;
-
Avoid burning waste materials on site wherever
possible. Never use petrol or similar accelerant's to start
or encourage fires;
-
Make sure everyone abides by site rules on
smoking.
-
Site rules for preventing fire are useless
unless they are followed. Employers and construction managers
should monitor their worksites and take appropriate action
when breaches are found.
Preparing for fire if it happens
Fires can grow extremely rapidly. If a construction
fire occurs the primary aim is to ensure that all those on site
reach safety as soon as possible. Delay can be fatal. Site staff
may need to fight a fire to enable their escape, but tackling
larger fires is the fire brigade's task.
Raising the alarm
- If fire breaks out the alarm should be
raised as soon as the first person discovers it.
- The type of alarm needed can range from
a simple shout of 'fire', to manual bells or klaxons or to sophisticated
automatic systems. Whatever system is chosen make sure that
it:
- Can be heard by everyone working on
site over normal background noise;
- Will work when needed (check that
existing building alarm systems have not been disconnected
if you rely on them during refurbishment work);
- Can be activated immediately (delay
can be fatal).
Means of escape
Construction sites can pose particular problems
because the routes in and out may be incomplete and obstructions
may be present. Open sites usually offer plentiful means of escape
and special arrangements are unlikely to be necessary. In enclosed
buildings people can easily become trapped, especially where they
are working above or below ground level. In such cases means of
escape need careful consideration. Make sure that:
- Wherever possible, there are at least two escape
routes in different directions;
- Travel distances to safety are reduced to a
minimum;
- Enclosed escape routes, for example corridors
or stairwells, can resist fire and smoke ingress from the surrounding
site. Where fire doors are needed for this make sure they are
provided and kept closed (self-closing devices should be fitted
to doors on enclosed escape routes);
- Escape routes and emergency exits are clearly
signed;
- Escape routes and exits are kept clear. Emergency
exits should never be locked when people are on the site;
- Emergency lighting is installed if necessary
to enable escape. This is especially important in enclosed stairways
in multi-storey structures which will be in total darkness if
the normal lighting fails during a fire;
- An assembly point is identified where
everyone can gather and be accounted for.
Fire-fighting equipment
The equipment needed depends on the risk of fire
occurring and the likely consequences if it does. It can range
from a single extinguisher on small low-risk sites to complex
fixed installations on large and high-risk sites. Whatever equipment
is needed make sure that:
- Fire equipment is located where it is really
needed and is easily accessible;
- The location of fire-fighting equipment and
how to use it is clearly indicated;
- The right sort of extinguishers are provided
for the type of fire that could occur. A combination of water
or foam extinguishers for paper and wood fires and CO2 extinguishers
for fires involving electrical equipment is usually appropriate;
- The equipment provided is maintained and works.
- Fire-fighting equipment should be checked regularly
by a competent person - often from the manufacturer;
- Those carrying out hot work have appropriate
fire extinguishers with them and know how to use them.
Emergency plans
The purpose of emergency plans is to ensure that
everyone on site reaches safety if there is a fire. Small and
low-risk sites only require very simple plans, but higher risk
sites will need more careful and detailed consideration. An emergency
plan should:
- Be available before work starts;
- Be up to date and appropriate for the circumstances
concerned;
- Make clear who does what during a fire;
- Where CDM applies be incorporated in the construction
phase health and safety plan;
- Work if it is ever needed.
- On larger high risk sites fire drills may be appropriate.
- On smaller sites, you should know what you need
to do if there is a fire;
- Managers need to make sure that everyone on their
sites knows what to do;
- Regular checks should be made to ensure that
fire precautions are in place.
Providing information
Fire action notices should be clearly displayed
where everyone on site will see them, for example at fire points,
site entrances or canteen areas.
Check List
Emergencies
- Are there emergency procedures, eg for evacuating
the site in case of fire?
- Do people on site know what the procedures
are?
- Is there a means of raising the alarm, and
does it work?
- Is there a way to contact the emergency services
from site?
- Are there enough suitable escape routes and
are these kept clear?
- Is the first-aid provision good enough?
- Are suitable fire extinguishers provided?
Fire
- Is the quantity of flammable materials, liquids
and gases kept to a minimum?
- Are they properly stored?
- Are flammable gas cylinders returned to a ventilated
store at the end of the shift?
- Are smoking and other ignition sources banned
in areas
- Where gases or flammable liquids are stored
or used?
- Are gas cylinders, associated hoses and equipment
properly maintained and in good condition?
- When gas cylinders are not in use, are the
valves fully closed?
- Is flammable and combustible waste removed
regularly and stored in suitable bins or skips?
- Are suitable fire extinguishers provided?
References
The
Construction (Design and Management) Regulations 2007 (CDM 2007)
Managing health and safety in construction. Construction
(Design and Management) Regulations 2007. Approved Code of Practice
L144 HSE Books 2007 ISBN 978 0 7176 6223 4
Health and safety in construction HSG150(Third
edition) HSE Books 2006 ISBN 978 0 7176 6182 4
Fire safety in construction work HSG168 HSE Books
1997 ISBN 0 7176 1332 1
Workplace health, safety and welfare. Workplace
(Health, Safety and Welfare) Regulations 1992. Approved Code of
Practice L24 HSE Books 1992 ISBN 978 0 7176 0413 5
|